Thoughts About the Renovation
Week 12 - June 22 - 26
Pipe is being installed for sprinklers on the third floor of the Luther Building.
Week 11 - June 15 - 19
Sprinkler installation for Geneva Hall is complete. Sprinkler installation continues in Knox and Luther Buildings.
Week 10 - June 8 - 12
Work begins on the Sanctuary ceiling and sprinkler installation on the 3rd and 1st floor of the Luther Building.
Week 9 - June 1 - 5
Sprinkler installation completed in Pickard Hall.
Week 8 - May 25 - 29
Sprinkler installation is proceeding.
Week 7 - May 18-22
Work continues. The scaffold platform is ready for ceiling work.
Week 6 - May 10-15
Scaffolding is up. Next the ceiling work begins.
Week 5 - May 4-8
Scaffolding begins going up.
Week 4 - April 27-May 1
The preacher snuffer is down.
Week 3 - April 20-25
Demolition is proceeding. The marble flooring has been removed.
Week 2
Demolition continues in Jane Bell and in the sanctuary.
Week 1
Sanctuary renovations began on April 6. We started by moving furnishing out and then progressed to demolition. The organ is secured, pews have been pulled and the lectern and pulpit have been removed so that they can be refurbished.